项目经理指出,一名位于另一个地点的团队成员总是错过最后期限。由于这会影响到项目进度,项目经理应该怎么做?The project manager indicates that a team member in another location always missed the deadline. Since this will affect the progress of the project, what should the project manager do?

发布于 2021-04-19 22:41:39
【单选题】
A 将该团队成员的工作重新分配给本地成员 To reassign the member's work to a local member
B 考虑将该成员的工作承包给本地供应商 To consider contracting the member's work to a local supplier
C 管理没有该成员的项目,并将此标记为项目相关方的风险 To manage the project without this member and mark this as the project stakeholders ' risk
D 与该成员沟通,了解其情况,并提供指导和支持 To communicate with the member to understand the situation and provide guidance and support