在遵循Scrum框架执行的软件开发项目的最后一个冲刺期间,一个关键的相关方请求进行更改,该更改可能会提高最终产品的性能,但也可能会影响计划的时间表。产品负责人应该怎么做?During the last sprint of a software development project that is being executed by following the Scrum framework, a key stakeholder requests a change that may improve the performance of the final product but may also affect the planned schedule. What should the product owner do?

发布于 2021-04-24 23:09:30
【单选题】
A 拒绝更改,因为其超出项目范围。 Reject the change as its out of project scope.
B 与团队一起分析新需求并检查重构选项。 ana-lyze the new requirement with the team and check options for refactoring.
C 发出正式的更改请求。 Issue a formal change request.
D 将情况上报高级管理层。 Escalate the situation to the senior management.

查看更多

关注者
0
被浏览
91
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题

手机
浏览

扫码手机浏览

分享
好友

在线
客服