【单选题】
A 分析对进度计划和预算的影响,并遵循变更请求过程 ana-lyze the impact on schedule planning and budgeting, and follow the change request process
B 寻求客户批准,以便变更进度计划 Seek customer approval to change the schedule
C 分析对进度计划和预算的影响,并要求客户批准这些变更 ana-lyze the impact on schedule plans and budgets and ask customers to approve these changes
D 更新进度计划,将该制约因素纳入其中 Update the schedule to include this constraint