某市的高铁项目正在接受市政会审查,原因是项目屡次请求增加预算和延长进度计划,以应对意外风险事件。该项目当前预测的经济问题将超过成本预支,项目经理该做什么?A high-speed rail project in a city is being reviewed by the council after repeated requests for budget increases and schedule extensions to deal with unexpected risk events. What should the project manager do if the economic problems currently projected for the project exceed the cost advance?

发布于 2021-04-24 23:09:25
【单选题】
A 接受相关风险,继续推进当前计划 Accept the risks and move forward with the current plan
B 请求增加应急资金,以管理任何无法预见的风险 Request additional contingency funds to manage any unforeseen risks
C 对当前风险管理过程的有效性进行风险审查 Conduct a risk review of the effectiveness of the current risk management process
D 提交变更请求,以供市政会审查 Submit a change request for review by the city council