【单选题】
A 告诉敏捷项目经理,让他们向团队传递信息。 Tell the agile project manager and let them pass the message to the team.
B 告诉关键相关方,最好的办法是在下次冲刺计划会议上提出来,到时再讨论。 Tell key stakeholders that the best approach is to bring it up at the next sprint planning meeting and discuss it later.
C 召开团队会议,解释你在冲刺中期要增加一个增量。 Hold a team meeting and explain that you are going to add an increment in the middle of the sprint.
D 向相关方解释,这个功能将被放在积压的后面,以便将来可能重新审视,但现在客户认为它没有价值。 Explain to interested parties that this feature will be placed at the back of the backlog for possible revisiting in the future, but for now customers see it as having no value.